§ 11.4. Procedure for a hearing before the planning commission.  


Latest version.
  • 11.41

    An application to approve a subdivision plat should be submitted in writing to the office of the Zoning Administrator at least 30 days prior to the regularly scheduled meeting of the City Planning Commission. The application must be on official City forms and must be accompanied by data, maps and plans that are adequate, in the opinion of the Zoning Administrator, to support the application.

    11.42

    The application shall come before the Planning Commission at its next regular meeting following receipt of a correctly completed application and staff report on same.

    11.43

    Before acting on any application requiring a public hearing, the Planning Commission shall ensure that proper legal notice is given.

    11.44

    The Planning Commission shall take action on applications for a subdivision plat within 30 days from the date of submission of the plat.

    11.45

    Any application may be withdrawn prior to action thereon by the Planning Commission at the discretion of the applicant initiating the request upon written notice to the Zoning Administrator.

    11.46

    A property owner, or his appointed agent, shall not initiate action affecting the same parcel of land more often than once every 12 months.

(Ord. No. 02-2014, § 4, 4-21-2014)