§ 10.2. Plan submission and review.  


Latest version.
  • Whenever the area to be disturbed comprises more than one acre, four (4) copies of the plan shall be filed with the Zoning Administrator at the time of application for a Land Use Certificate and Building Permit. A copy of the plans shall also be on file at the job site. If the Zoning Administrator and/or the City Engineer determines, either upon review of such plan or on inspection of the job site, that a significant risk of off-site sedimentation or erosion exists, he will require that a revised plan be prepared. Pending the preparation of the revised plan, the work shall be either suspended or continued under conditions outlined by the Building Inspector or the City Engineer. The applicant shall be responsible for all fees and costs incurred during the review process.